Document Citation: 73 P.S. § 180

Header:

PENNSYLVANIA STATUTES
TITLE 73. TRADE AND COMMERCE
CHAPTER 3. EXPLOSIVES, REGULATION
EXCAVATION AND DEMOLITION


Date:
08/31/2009

Document:

NOTICE: As to expiration of this section on December 31, 2016, see 73 P.S. § 182.7.

§ 180. Excavators, duties


It shall be the duty of each excavator who intends to perform excavation or demolition work within this Commonwealth:

(1), (2) Deleted by 1996, Dec. 19, P.L. 1460, No. 187, § 3, imd. effective.

(2.1) To request the location and type of facility owner lines at each site by notifying the facility owner through the One Call System. Notification shall be not less than three nor more than ten business days in advance of beginning excavation or demolition work. No work shall begin earlier than the scheduled excavation date which shall be on or after the third business day after notification. The scheduled excavation date shall exclude the date upon which notification was received by the One Call System and notification received on a Saturday, Sunday or holiday, which shall be processed on the following business day. In the case of a complex project, notification shall not be less than ten business days in advance of the beginning of excavation or demolition work.

(2.2) To provide the One Call System with specific information to identify the site so that facility owners might provide indications of their lines. An excavator shall be deemed to have met the obligations of clause (2.1) if he calls the One Call System, provides the site and other required information and receives a serial number.

(3) In a complex project or if an excavator intends to perform work at multiple sites or over a large area, he shall take reasonable steps to work with facility owners, including scheduling and conducting a preconstruction meeting, so that they may locate their facilities at a time reasonably in advance of the actual start of excavation or demolition work for each phase of the work. A preconstruction meeting may take place at any time prior to the commencement of excavation or demolition work, and the excavator, facility owners and designer, or their agents, shall attend the meeting. Notice of the meeting shall be given sufficiently in advance so as to permit attendance, either in person or electronically, by the excavator, facility owners and designer, or their agents, and shall include information sufficient to identify the scope of work. If the excavator does not believe that a preconstruction meeting is necessary under the circumstances of this paragraph it shall indicate such belief in its notice, but any facility owner with facilities at the site may request a meeting with the excavator, and a meeting shall be held between the facility owner and the excavator. After commencement of excavation or demolition work, the excavator shall be responsible for protecting and preserving the staking, marking or other designation until no longer required for proper and safe excavation or demolition work at or near the underground facility, or by contacting the One Call System to request that the facilities be marked again in the event that the previous markings have been compromised or eliminated.

(3.1) To comply with the requirements established by the One Call System as determined by the board of directors regarding the maximum area that a notification may cover.

(4) To exercise due care; and to take all reasonable steps necessary to avoid injury to or otherwise interfere with all lines where positions have been provided to the excavator by the facility owners pursuant to clause (5) of section 2 Within the tolerance zone the excavator shall employ prudent techniques, which may include hand-dug test holes, to ascertain the precise position of such facilities. If insufficient information to safely excavate is available pursuant to clause (5) of section 2, the excavator shall employ like prudent techniques which shall be paid for by the project owner pursuant to clause (15) of this section.

(5) If the facility owner fails to respond to the excavator's timely request as provided under clause (5) of section 2 or the facility owner notifies the excavator that the line cannot be marked within the time frame and a mutually agreeable date for marking cannot be arrived at, the excavator may proceed with excavation as scheduled, but not earlier than the lawful dig date, provided he exercises due care in his endeavors, subject to the limitations contained in this clause and clauses (2.1) through (4).

(6) To inform each operator employed by the excavator at the site of such work of the information obtained by the excavator pursuant to clauses (2.1) through (5), and the excavator and operator shall:

(i) Plan the excavation or demolition to avoid damage to or minimize interference with a facility owner's facilities in the construction area. Excavation or demolition work which requires temporary or permanent interruption of a facility owner's service shall be coordinated with the affected facility owner in all cases.

(ii) After consulting with a facility owner, provide such support and mechanical protection for known facility owner's lines at the construction site during the excavation or demolition work, including during backfilling operations, as may be reasonably necessary for the protection of such lines.

(7) To report immediately to the facility owner any break or leak on its lines, or any dent, gouge, groove or other damage to such lines or to their coating or cathodic protection, made or discovered in the course of the excavation or demolition work. The One Call System board of directors may adopt procedures to permit reporting under this clause through the One Call System.

(8) To immediately notify 911 and the facility owner if the damage results in the escape of any flammable, toxic or corrosive gas or liquid which endangers life, health or property. The excavator shall take reasonable measures, based on its knowledge, training, resources, experience and understanding of the situation, to protect themselves and those in immediate danger, the general public, the property and the environment until the facility owner or emergency responders have arrived and completed their assessment and shall remain on site to convey any pertinent information to responders that may help them to safely mitigate the situation.

(9) The time requirements of clause (2.1) shall not apply to a facility owner or excavator performing excavation or demolition work in an emergency, as defined in section 1; nonetheless, all facility owners shall be notified as soon as possible before, during or after excavation or demolition, depending upon the circumstances.

(10) Deleted by 1996, Dec. 19, P.L. 1460, No. 187, § 3, imd. effective.

(11) An excavator shall use the color white to mark a proposed excavation site when exact site information cannot be provided.

(11.1) To assist a facility owner in determining involvement of a facility owner's lines by disclosing additional available information requested by the facility owner, including dimensions and the direction of proposed excavations.

(11.2) If using horizontal directional drilling (HDD), at a minimum, to utilize the best practices published by the HDD Consortium.

(12) The following standards shall be applied in determining whether an excavator shall incur any obligation or be subject to liability as a result of an excavator's demolition or excavation work damaging a facility owner's facilities:

(i) The excavator who has complied with the terms of this act and who was not otherwise negligent shall not be subject to liability or incur any obligation to facility owners, operators, project owners or other persons who sustain injury to person or property as a result of the excavator's excavation or demolition work damaging a facility owner's lines.

(ii) Where an excavator has failed to comply with the terms of this act or was otherwise negligent, and the facility owner or designer has misidentified, mislocated or failed to identify its facilities pursuant to this act, then in computing the amount of reimbursement to which the facility owner is entitled, the cost of repairing or replacing its facilities shall be diminished in the same proportion that the facility owner's or designer's misidentification, mislocation or failure to identify the facilities contributed to the damage. Should the facility owner or designer not have misidentified, mislocated or failed to identify its facilities pursuant to this act, there shall be no diminution of the facility owner's right of recovery.

(13) If, after receiving information from the One Call System or directly from a facility owner, the excavator decides to change the location, scope or duration of a proposed excavation, the obligations imposed by this section shall apply to the new location.

(14) If an excavator removes its equipment and vacates a worksite for more than two business days, he shall renotify the One Call System unless other arrangements have been made directly with the facility owners involved in his worksite.

(15) When the information required from the facility owner under clause (5)(i) of section 2 cannot be provided or, due to the nature of the information received from the facility owner, it is reasonably necessary for the excavator to ascertain the precise location of any line or abandoned or unclaimed lines by prudent techniques, which may include hand-dug test holes, vacuum excavation or other similar devices, the excavator shall promptly notify the project owner or the project owner's representative, either orally or in writing. If oral notification is given, the notice shall be reduced to writing within a reasonable time by the project owner or excavator. After giving such notice, the excavator shall be entitled to compensation from the project owner for this additional work as provided in the latest edition of the Pennsylvania Department of Transportation Form 408 specifications for extra work performed on a force account basis. The provisions of this subsection shall not be deemed to limit any other rights which the excavator has under its contract with the project owner or otherwise. Provisions in any contract, public or private, which attempt to limit the rights of excavators under this section shall not be valid for any reason, and any attempted waiver of this section shall be void and unenforceable as against public policy and any such attempted waiver shall be reported to the department.

(16) To submit an incident report to the department not more than ten business days after striking or otherwise damaging a facility owner's line during excavation or demolition activities that resulted in personal injury or property damage to parties other than the affected excavator or facility owner. In addition, the incident report may be furnished to the Pennsylvania Public Utility Commission and the Pennsylvania Emergency Management Agency pursuant to memoranda of understanding negotiated between these agencies and the department.

(17) To comply with all requests for information by the department relating to the department's enforcement authority under this act within thirty days of the receipt of the request.

(18) To, if it chooses to do so and if working for a facility owner, a municipality or a municipal authority, delegate the power to discharge the duties set forth in clauses (2.1) and (2.2) to its project owner, with the project owner's consent. If the power is delegated pursuant to this clause, both the excavator and the project owner shall be responsible for providing the required notices.

(19) To ensure the accuracy of any information provided to the One Call System pursuant to this section.